Q1. The rate of payment is made for 100 cu m (per % cu m) in case of

(A) Earth work in excavation
(B) Rock cutting
(C) Excavation in trenches for foundation
(D) All the above

Show Answer

Answer: (D) All the above


Q2. Pick up the correct statement from the following:

(A) The earth work of cutting in trenches or borrow pits in fairly uniform ground is measured with the help of average depths of the dead men
(B) The earth work in trenches or borrow pits in irregular ground is measured by taking the difference in levels before and after completion of work
(C) The earth work in trenches or borrow pits, where neither a nor b is feasible, are measured from the fillings after deduction of voids
(D) All the above

Show Answer

Answer:(D) All the above





Q3. For the construction of buildings, the subheads of the estimate are

(A) Earthwork, Concrete work, Brick work
(B) Brickwork, Stone work, Roofing
(C) Brickwork Flooring, Wood work, Steel work
(D) All the above

Show Answer

Answer:(D) All the above


Q4. The rate of an item of work depends on

(A) Specifications of works
(B) Specifications of materials
(C) Proportion of mortar
(D) All the above

Show Answer

Answer: (D) All the above


Q5. The cross-sections for a highway is taken at

(A) Right angle to the centre line
(B) 30 meters apart
(C) Intermediate points having abrupt change in gradient
(D) All the above

Show Answer

Answer: (D) All the above


Q6. Pick up the correct statement from the following:

(A) Pointing is measured in sq.m
(B) Plastering is measured in sq.m
(C) Glazing is measured in sq.m
(D) All the above

Show Answer

Answer: (D) All the above


Q7. The main factor to be considered while preparing a detailed estimate, is

(A) Quantity of the materials
(B) Availability of materials
(C) Transportation of materials
(D) All the above

Show Answer

Answer: (D) All the above


Q8. Referring of given figure, pick up the correct statement from the following:

https://cbsemcq.com/wp-content/uploads/2021/08/ob-civ-es-SET-1-Q8.png

(A) The total length of centre line of four walls is 20 m
(B) Length of long wall out-to-out is 6.80 m
(C) Length of short walls in-to-in is 3.20 m
(D) All the above

Show Answer

Answer: (D) All the above


Q9. The cross-section of a road partly in banking and partly in cutting is shown in the given figure. The area of the shaded portion is

https://cbsemcq.com/wp-content/uploads/2021/08/ob-civ-es-SET-1-Q-9.png

(A) ⅓ × (b – rd)²/(r – s)
(B) ⅓ × (b – rd)²/(r + s)
(C) ½ × (b + rd)²/(r – s)
(D) ⅓ × (b – rd)²/(s – r)

Show Answer

Answer: (A) ⅓ × (b – rd)²/(r – s)


Q10. Pick up the correct statement from the following:

(A) The estimated value of the work excluding the amount for contingencies, work charged establishment, tool and plants, is called work value
(B) The actual expenditure involved to complete a work including incidental, establishment and travelling charges, is called actual cost
(C) The formal acceptance by the administrative department for incurring an expenditure on the work, is called administrative approval
(D) All the above

Show Answer

Answer: (D) All the above


Q11. Pick up the correct statement regarding the centre line method of estimating a building

(A) Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item
(B) The centre line is worked out separately for different sections of walls of a building
(C) The centre line length is reduced by half the layer of main wall joining the partition wall
(D) All the above

Show Answer

Answer: (D) All the above


Q12. Pick up the correct statement from the following:

(A) If the bed level is above N.S.L. the canal is called fully in baking and the berms are designed as 3 d where d is full supply depth of water (F.S.D.)
(B) Area of canal in cutting = BD + Sd2 where B = bed width, d = depth of cutting and S is the side slope
(C) If F.S.L. is above N.S.L the canal is called partly in cutting and partly in filling and berms are designed as 2d where d is full supply depth
(D) All the above

Show Answer

Answer: (D) All the above


Q13. Brick walls are measured in sq. m if the thickness of the wall is

(A) 10 cm
(B) 15 cm
(C) 20 cm
(D) None of these

Show Answer

Answer: (A) 10 cm


Q14. According to Indian Standards Institute, the actual size of modular bricks is

(A) 23 cm × 11.5 cm × 7.5 cm
(B) 25 cm × 13 cm × 7.5 cm
(C) 19 cm × 9 cm × 9 cm
(D) 20 cm × 10 cm × 10 cm

Show Answer

Answer: (C) 19 cm × 9 cm × 9 cm


Q15. Pick up the incorrect statement from the following:

(A) No deduction is made for the volume occupied by reinforcement
(B) No deduction is made for the openings upto 0.1 sq.m
(C) No deduction is made for volumes occupied by pipes, not exceeding 100 sq.cm in cross-section
(D) None of these

Show Answer

Answer: (D) None of these

 

 

Estimating Costing and Valuation Objective Question – Set 02

 


Q8. The area of the cross-section of a road fully in banking shown in the given figure, is

https://cbsemcq.com/wp-content/uploads/2021/08/ob-civ-es-SET-2-Q8.png

(A) [sb² + r² (2bd + sd)²]/(r² – s²)
(B) [sb² + r² (2bd + sd)²]/(r² – s5)
(C) [sb² + r² (2bd + sd)²]/(r – s)
(D) None of these

Show Answer

Answer: (A) [sb² + r² (2bd + sd)²]/(r² – s²)


Q9. As per Indian Standard Specifications, the peak discharge for domestic purposes per capita per minute, is taken

(A) 1.80 liters for 5 to 10 users
(B) 1.20 liters for 15 users
(C) 1.35 for 20 users
(D) All the above

Show Answer

Answer: (D) All the above


Q10. A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is

(A) 500 m3
(B) 1000 m3
(C) 1500 m3
(D) 2000 m3

Show Answer

Answer: (C) 1500 m3


Q11. Cost of fittings and their fixing is specified for the following sanitary fittings

(A) Water closets
(B) Flushing pipes
(C) Lavatory basins
(D) All the above

Show Answer

Answer: (D) All the above


Q12. In long and short wall method of estimation, the length of long wall is the centre to centre distance between the walls and

(A) Breadth of the wall
(B) Half breadth of wall on each side
(C) One fourth breadth of wall on each side
(D) None of these

Show Answer

Answer: (B) Half breadth of wall on each side


Q13. While estimating the qualities for the construction of a building, the correct metric unit is

(A) Meter for length
(B) Cubic metre for area
(C) Square meters for volume
(D) Liter for capacity

Show Answer

Answer: (D) Liter for capacity


Q14. The excavation exceeding 1.5 m in width and 10 sq.m in plan area with a depth not exceeding 30 cm, is termed as

(A) Excavation
(B) Surface dressing
(C) Cutting
(D) Surface excavation

Show Answer

Answer: (D) Surface excavation


Q15. The expected out turn of cement concrete 1 : 2 : 4 per mason per day is

(A) 1.5 m3
(B) 2.5 m3
(C) 3.5 m3
(D) 5.0 m3

Show Answer

Answer: (D) 5.0 m3

 

Estimating and Costing in Civil Engineering Objective – Set 03

 

Q1. Pick up the correct statement from the following:

(A) In order to check up the average depth of excavation, ‘Dead man’s’ are left at the mid-widths of borrow pits
(B) The earthwork calculation in excavation is made from the difference in levels obtained with a level
(C) The earth work in excavation to form the road embankment includes the formation of correct profile and depositing the soil in layers
(D) All the above

Show Answer

Answer: (D) All the above


Q2. The value of ‘C’ of Indian type W.C. shown in the given figure is:

https://cbsemcq.com/wp-content/uploads/2021/08/ob-civ-es-SET-3-Q2.png

(A) 400 mm
(B) 450 mm
(C) 500 mm
(D) 550 mm

Show Answer

Answer:(C) 500 mm


Q3. The item of the brick structure measured in sq.m, is

(A) Reinforced brick work
(B) Broken glass coping
(C) Brick edging
(D) Brick work in arches

Show Answer

Answer: (B) Broken glass coping


Q4. The concrete work for the following part of the building of specified thickness is measured in square meters

(A) Root slabs
(B) Floors
(C) Wall panels
(D) All the above

Show Answer

Answer:(D) All the above


Q5. The brick work is not measured in cu m in case of

(A) One or more than one brick wall
(B) Brick work in arches
(C) Reinforced brick work
(D) Half brick wall

Show Answer

Answer: (D) Half brick wall


Q6. The area is measured correct to the nearest

(A) 0.01 sqm
(B) 0.02 sqm
(C) 0.03 sqm
(D) 0.04 sqm

Show Answer

Answer: (A) 0.01 sqm


Q7. The most reliable estimate is

(A) Detailed estimate
(B) Preliminary estimate
(C) Plinth area estimate
(D) Cube rate estimate

Show Answer

Answer: (A) Detailed estimate


Q8. The expected out turn of 12 mm plastering with cement mortar is

(A) 2.5 sq m
(B) 4.0 sq m
(C) 6.0 sq m
(D) 8.0 sq m

Show Answer

Answer: (D) 8.0 sq m


Q9. Pick up the incorrect statement from the following:

(A) Lead is the average horizontal straight distance between the borrow pit and the place of spreading soil
(B) The lead is calculated for each block of the excavated area
(C) The unit of lead is 50 m for a distance upto 500 m
(D) The unit of lead is 1 km where the lead exceeds 2 km

Show Answer

Answer:(D) The unit of lead is 1 km where the lead exceeds 2 km


Q10. The measurement is not made in square meters in case of

(A) D.P.C. (Damp proof course)
(B) Form works
(C) Concrete Jeffries
(D) R.C. Chhajja

Show Answer

Answer: (D) R.C. Chhajja


Q11. The reduced levels of points, 30 metres apart along the longitudinal section of a road portion between chainages 5 and 9 are shown in the given figure. If there is a uniform up-gradient of the road 120 in 1, the chainage of the point with no filling or cutting is

https://cbsemcq.com/wp-content/uploads/2021/08/ob-civ-es-SET3-Q11.png

(A) (6 + 15) chains
(B) (6 + 12) chains
(C) (6 + 18) chains
(D) None of these

Show Answer

Answer: (B) (6 + 12) chains


Q12. The total length of a cranked bar through a distance (d) at 45° in case of a beam of effective length L, is

(A) L + 0.42 d
(B) L + (2 × 0.42 d)
(C) L – (0.42 d)
(D) L – (2 × 0.4 d)

Show Answer

Answer: (B) L + (2 × 0.42 d)


Q13. The assumption on which the trapezoidal formula for volumes is based, is

(A) The end sections are parallel planes
(B) The mid-area of a pyramid is half the average area of the ends
(C) The volume of the Prismoidal is over-estimated and hence a Prismoidal
(D) All the above

Show Answer

Answer: (D) All the above


Q14. The unit of measurement is per quintal for the following:

(A) Collapsible gates with rails
(B) Rolling shutters
(C) Expanded metal wire netting
(D) M.S. reinforcement of R.C.C. works

Show Answer

Answer: (D) M.S. reinforcement of R.C.C. works


Q15. In the mid-section formula

(A) The mean depth is the average of depths of two consecutive sections
(B) The area of mid-sections is calculated by using mean depth
(C) The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections
(D) All of the above

Show Answer

Answer: (D) All of the above

 

Objective of Estimating and Costing – Set 04

 


Q15. The correct Prismoidal formula for volume is

(A) D [first area + last area + Ʃ Even area + 2 Ʃ odd areas]
(B) D/3 [first area + last area + 4 Ʃ Even area + 2 Ʃ odd areas]
(C) D/3 [first area + last area + 2 Ʃ Even area + 4 Ʃ odd areas]
(D) D/6 [first area + last area + 2 ∑ Even area + 4 ∑ odd areas]

Show Answer

Answer: (B) D/3 [first area + last area + 4 Ʃ Even area + 2 Ʃ odd areas]

 

Estimating and Costing MCQ pdf – Set 05

 


Q15. The value of ‘A’ of Indian type W.C. shown in the given figure is:

https://cbsemcq.com/wp-content/uploads/2021/08/ob-civ-es-SET-5-Q15.png

(A) 25 cm
(B) 30 cm
(C) 40 cm
(D) 45 cm

Show Answer

Answer: (B) 30 cm

 

 

Estimating and Costing MCQ questions – Set 06

 

 

Q1. The diameter of a domestic sewer pipe laid at gradient 1 in 100 is recommended

(A) 100 mm
(B) 150 mm
(C) 200 mm
(D) 175 mm

Show Answer

Answer: (B) 150 mm


Q2. Pick up the item whose weight is added to the weight of respective item, is

(A) Cleats
(B) Brackets
(C) Bolts
(D) All the above

Show Answer

Answer: (D) All the above


Q3. For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is

(A) 0.90 m3
(B) 0.94 m3
(C) 0.98 m3
(D) 1.00 m3

Show Answer

Answer: (B) 0.94 m3


Q4. The order of booking dimensions is

(A) Length, breadth, height
(B) Breadth, length, height
(C) Height, breadth, length
(D) None of these

Show Answer

Answer: (A) Length, breadth, height


Q5. The expected out turn for earth work in excavation in ordinary soil per workman per day is

(A) 1.00 cum
(B) 2.00 cum
(C) 3.00 cum
(D) 4.00 cum

Show Answer

Answer:(C) 3.00 cum


Q6. Size, capacity and materials need be specified for

(A) Bib-cocks
(B) Stop-cocks
(C) Ball valves
(D) All the above

Show Answer

Answer: (D) All the above


Q7. Pick up the incorrect statement regarding a master trap from the following:

(A) It is provided in between the lower end of the house drain and the street sewer
(B) It is provided a cleaning eye at the top of the trap
(C) The mica flap valve which opens inwards only, is fitted at the top of the inlet pipe
(D) The water seal is less than that of ordinary traps

Show Answer

Answer: (D) The water seal is less than that of ordinary traps


Q8. The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is

(A) 1.00 m3
(B) 1.25 m3
(C) 1.50 m3
(D) 1.75 m3

Show Answer

Answer: (B) 1.25 m3


Q9. The expected out turn of half brick partition wall per mason per day is

(A) 1.5 m3
(B) 2.0 m3
(C) 4.0 m2
(D) 5.0 m2

Show Answer

Answer: (B) 2.0 m3


Q10. The area of a sloping surface of a protective embankment of mean height‘d’, side slopes S: 1 and length ‘L’ is

(A) d × d × s
(B) √[d2 × (ds)2]
(C) L.D √(1 + s2)
(D) 2 L.D √(1 + s2)

Show Answer

Answer: (C) L.D √(1 + s2)


Q11. The brick work is measured in sq metre, in case of

(A) Honey comb brick work
(B) Brick flat soling
(C) Half brick walls or the partition
(D) All the above

Show Answer

Answer: (D) All the above


Q12. The floor area includes the area of the balcony up to

(A) 100 %
(B) 75 %
(C) 50 %
(D) 25 %

Show Answer

Answer:(C) 50 %


Q13. The detention period in a septic tank is assumed

(A) 20 minutes
(B) 25 minutes
(C) 30 minutes
(D) 40 minutes

Show Answer

Answer: (C) 30 minutes


Q14. The height of the sink of wash basin above floor level is kept

(A) 60 cm
(B) 70 cm
(C) 75 cm to 80 cm
(D) 80 cm

Show Answer

Answer: (C) 75 cm to 80 cm


Q15. The slope of the outlet of ‘P trap’ below the horizontal is kept

(A) 8°
(B) 10°
(C) 12°
(D) 14°

Show Answer

Answer: (D) 14°


Q16. If B is the width of formation, d is the height of the embankment, side slope S : 1, for a highway with no transverse slope, the area of cross-section is

(A) B + d + Sd
(B) Bd + Sd2
(C) B × d – Sd1/2
(D) ½ (Bd + Sd2)

Show Answer

Answer: (B) Bd + Sd2


Q17. For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is

(A) 0.200 m3
(B) 0.247 m3
(C) 0.274 m3
(D) 0.295 m3

Show Answer

Answer: (C) 0.274 m3


Q18. The weight of an item is measured correct to nearest

(A) 0.25 kg
(B) 0.50 kg
(C) 0.75 kg
(D) 1.00 kg

Show Answer

Answer: (D) 1.00 kg


Q19. The item of steel work which is measured in sq.m, is

(A) Collapsible gates
(B) Rolling shutters
(C) Ventilators and glazing
(D) All the above

Show Answer

Answer: (D) All the above


Q20. Berms are provided in canals if these are

(A) Fully in excavation
(B) Partly in excavation and partly in embankment
(C) Fully in embankment
(D) All the above

Show Answer

Answer: (C) Constant in time and space

 